Free for life: Get a Quote and Book Online buttons for your website. Create my widgets →Need a website? $25/mo or $500 once →
ReportWalk

Construction

Construction Quality Control Form

A construction quality control inspection form for any trade at any phase: submittals and readiness, a list of workmanship checks by activity and location — each against its drawing or spec reference, with the value measured — then materials in the work, tests and hold points, and protection of finished work. Every nonconforming check gets the defect, its cause, a disposition, a corrective action and a re-inspection.

Free — no account, no trial, no card.

Fill this in and download the finished PDF. Your answers stay on this device as you type. We ask for an email address once, at the download.

This form checks work once it is built. Checking a delivery at the gate — the ticket against the order, the count, the grade, damage and certificates — has its own page: Material receiving inspection

0 of 50 answered0%
1

Project and Inspection

Which job, which areas and trades, which phase, and what you are checking against.

Tell me what you seeSign in to talk instead of typing.

Levels, rooms, gridlines or units — so nobody assumes an area was checked when it was not.

Foremen, engineer, owner's rep — with their companies.

2

Plan, Submittals and Readiness

Is the paperwork behind this work in order before you judge the work itself?

Tell me what you seeSign in to talk instead of typing.

If there is none, mark No and say in the notes what you checked against instead.

Check the set at the workface, not the one in the trailer.

3

Workmanship by Activity

One entry per check: an activity, a location, a requirement — and whether the work meets it.

Tell me what you seeSign in to talk instead of typing.

Add one entry for each thing you checked in each location. Give the drawing or spec clause, say what you checked and what you measured or saw, then mark the result. Only a check that does not conform asks for the defect, cause, disposition and fix.

Quality checks*

Nothing added yet.

4

Materials in the Work

What has been built in, and what is waiting to be — is it the approved product, in good order?

Tell me what you seeSign in to talk instead of typing.

Read the labels, stamps or tags on the material itself.

0/6 · they go into your PDF and stay on this computer

5

Tests and Hold Points

Results that prove what the eye cannot, and the stops where someone must look first.

Tell me what you seeSign in to talk instead of typing.

Answer No and the questions under it fold away. It is not counted in the score.

6

Protection of Finished Work

Work that passed today still has to survive the trades that follow.

Tell me what you seeSign in to talk instead of typing.

Floor protection, corner guards, covered fixtures, sheeted openings.

0/6 · they go into your PDF and stay on this computer

7

Result, Actions and Sign-Off

Where the inspected work stands, what is owed, and who agrees.

Tell me what you seeSign in to talk instead of typing.
Corrective actions

Nothing added yet.

0/10 · they go into your PDF and stay on this computer

Sign above — Inspector
Sign above — Contractor
Sign above — Owner

Free, no account needed. Your answers never leave this browser.

A construction quality control form is the record that the work in place matches the drawings and the specification — checked by someone who looked, measured and wrote down what they found. It is the contractor's own proof of quality, and the first thing an owner, an architect or a lawyer asks for when something goes wrong later. This one is built around a list of checks: each activity, in each area, against the spec clause or drawing it has to meet, with the value you measured. Anything that does not conform gets a cause, a disposition, a corrective action and a re-inspection, so the record shows the loop closed rather than just the problem found. Tests and hold points have their own log. You can fill it in here and download a finished PDF without creating an account.

Quality control is not quality assurance

The two are often used as if they meant the same thing. Quality assurance is the system — the QC plan, the inspection and test plan, who is responsible for what, how nonconformances are handled. Quality control is the part done with a tape and a level on the job: checking that a particular wall, slab or duct run is what the documents call for.

This form is the quality control half. It works best when there is a plan behind it that says which activities are inspected, at what point and against what — but it is just as useful on a small job without one, because it makes you write down what you checked against.

Inspect at the moments that matter

Many contractor QC programs, including the three-phase system common on US federal work, inspect each definable feature of work at set points rather than at random. The phase question at the top of the form records which one this is.

  • Preparatory — before the work starts: submittals approved, materials on site and correct, drawings current, the crew briefed on the requirements.
  • Initial — as soon as the first representative piece of work is in place: is it being built the way the documents say, before the mistake is repeated across a whole floor?
  • Follow-up — regularly while the work continues, to make sure the standard set at the initial inspection is holding.
  • Completion — before the work is covered up or handed over, when it can still be seen and still be fixed cheaply.

Write every check against a reference

"Drywall looks good" is not a quality record. "Level 3, rooms 301–308, partitions per A-501 type 4: joints taped and finished to level 4, flatness within 1/8 in over 10 ft, measured 1/16 in at 304" is. The list here asks for the drawing or spec reference, what was checked, and what was measured or seen, so anyone reading the report later knows what conforms actually meant.

Keep each check to one location and one requirement. That way one can fail and be fixed without dragging the rest of the floor with it, and the re-inspection knows exactly where to go.

Nonconforming work: cause, disposition, re-inspection

When a check does not conform, the form asks four more things. What exactly is wrong and by how much. The likely cause — workmanship, material, the drawings, equipment, the weather, damage by a later trade — because the cause decides whether the fix is one wall or a change to how every wall is built. The disposition: rework, repair, replace, or use as is with the designer's written acceptance. And whether it has been re-inspected.

Anything that needs someone to come back goes in the corrective actions list with an owner, a date and the nonconformance report number if your project issues them. On the phone, Start a re-inspection turns every failed check into its own card — fixed, partly fixed, not fixed — with an after photo, and the follow-up report puts each one beside what you found the first time. Speak while you walk, and the document writes itself: say "east stair, handrail height thirty-two inches, spec says thirty-four" and the check fills in.

Tests and hold points

Some quality can only be proved by a test — compaction, concrete strength, weld examination, pressure tests, duct leakage — and some work must not continue until a named person has looked at it. The tests section logs each one with the requirement, the result and the report number, and treats a result that is still at the lab as pending rather than as a pass.

A hold point that was released before the work moved on is a pass. One the work went straight past without release is a failure, whatever the later test shows, because the chance to look has gone.

Common questions

What should a construction quality control form include?

The project, area and phase of work; what the work was checked against; a check-by-check record of each activity and location with the reference, the requirement and what was found; materials in the work; tests and hold points with their results; any nonconforming work with its cause, disposition and corrective action; and the signatures of the inspector and the contractor.

Who fills in a construction QC inspection?

Usually the contractor's quality control manager, superintendent or a trade foreman assigned to QC. Owners' representatives, construction managers and third-party inspectors use the same kind of record for their own quality assurance walks.

How often should quality control inspections be done?

At set points for each type of work rather than on a calendar: before it starts, when the first piece is in place, regularly while it continues, and before it is covered up. Daily QC reports are common on larger projects.

What is a nonconformance report?

A record that a piece of work or material does not meet the contract requirements, with what is wrong, how it will be dealt with and who accepted that decision. Many projects number them; this form has a place for that number on each corrective action.

Does this replace the building department or special inspections?

No. Code inspections and special inspections are separate, and only the authority or the special inspector can sign those off. This form records the contractor's or owner's own quality control, and can log those inspections as hold points.

Can I re-check only the items that failed?

Yes. In the ReportWalk app, start a re-inspection from this walk and only the failed checks come back, each asking whether it is fixed, with a photo. Re-inspections are free and do not count toward your plan.